At the Autumnwood courts, 11950 Walnut Branch Road, there are no reservations. Pickleball runs daily from 8 a.m. to 10 p.m., and players set their paddles in a stack to hold a spot in line for the next open court. The site has four lighted courts built for pickleball and two tennis courts that pickleball players share. Reston Association wants Autumnwood to become the place pickleball in Reston happens. The plan's tennis half is already funded and on the calendar for next year.
One staff memo split the sports
The Lake Newport and Autumnwood changes come from one decision. A July 2026 RA staff memo described the plan as removing tennis programming from Autumnwood and pickleball programming from Lake Newport "to create premier facilities for tennis (Lake Newport) and pickleball (Autumnwood)." Under the recommendation, Autumnwood would end up with eight dedicated pickleball courts.
Each half moved on its own track and at a different price.
| Lake Newport | Autumnwood | |
|---|---|---|
| Courts today | 6 lighted tennis courts, also lined for pickleball | 4 lighted pickleball courts, plus 2 shared tennis courts |
| Sport under the plan | Tennis only | Pickleball only, 8 courts |
| Estimated cost | $1.6 million in 2027, plus $300,000 collected in 2026 | About $75,000 |
| Where it stands | In the adopted 2027–2036 capital plan | Proposed in July 2026, member feedback taken in August |
Lake Newport is the large check in RA's 2027 capital plan
RA's capital plan calls the Lake Newport Tennis Court replacement "the highlight of the tennis category" for 2027. It calls the six lighted courts "the premier tennis facility in Reston." The funding shows $300,000 already collected in 2026 and $1.6 million budgeted for 2027.
That $1.6 million is a large share of RA's capital spending. According to FFXnow's coverage of the adopted budget, the 2027 capital budget totals $4.48 million, so one six-court facility accounts for about 36 cents of each capital dollar RA plans to spend next year. In the same budget cycle, the RA board raised the annual member assessment from $890 to $900 per property for 2027.
The project went through RA's Recreation Facilities Investment Process because of its size. Staff held on-site engagement twice, once in 2025 and once in 2026. The feedback changed between the two rounds:
- 2025: improve the playing surface, the lighting, the seating and the gazebo.
- 2026: mostly requests for an indoor facility at Lake Newport.
The 2027 priorities are the playing surface, lighting, more shade and a water bottle filling station. The gazebo is a separate phase scheduled for 2028. In July, RA staff shared designs from Rinker Design Associates, took comments online and met players at the courts on Aug. 5. The public comment window closed Aug. 14.
The renovation is scheduled for 2027. When the courts close and when they reopen will depend on the construction schedule.
Members asked for a larger Lake Newport project
Before the capital plan vote, the public hearing focused on everything around the courts. FFXnow reported that Julie Bitzer, chair of RA's Parks and Recreation Advisory Committee, suggested moving future Lake Newport projects, including the gazebo replacement, up to 2027. Other speakers asked for better lighting and paths, renovated bathrooms and a hitting wall. Reston resident Usman Zafar said, according to the same report:
"I'm so pleased to see the planned renovations moving forward. But I'd like to, as Julie stated, encourage the board to think beyond just the playing surfaces and consider the entire facility holistically."
The board voted on moving the gazebo from 2028 to 2027, and the motion failed. Staff told the board that some of the safety upgrades speakers wanted, namely new lighting at the court entrances and repaved pathways, are already part of the court renovation. RA CEO Peter Lusk said he would be "happy to have that conversation" about an earlier gazebo, but that a restroom and a hitting wall were bigger projects unlikely to happen before 2028. He pointed to the Hook Road improvements as a possible "prototype for adding restrooms around Reston."
South Lakes District Director Jennifer Jushchuk described the trade-off as "a balancing act between how quickly can construction get done and the courts reopened and how much of the project we can get done within the weather space that you have each year."
At the hearing, the requests for Lake Newport were about shade, the gazebo, restrooms, lighting and paths around the courts.
Autumnwood carries the pickleball half
The case for Autumnwood comes from RA's own counts. A summer survey found that more than 90% of court use there was pickleball and that tennis players had moved to other facilities. A staff tracking study from June 13 to July 5, 2026, counted 2,684 pickleball players at Autumnwood and measured overall court use at 66.1% of capacity, so on average some courts were still open.
Staff estimated a permanent conversion would cost about $75,000:
- Remove the tennis striping
- Add permanent pickleball striping
- Improve the court fencing
- Install permanent pickleball nets
- Add more shade
- Install a water bottle filling station
The staff recommendation set a date for the change of no later than Sept. 1, 2026. At its July 23 meeting, the board pushed the pickleball briefing and the Autumnwood decision to September. Patch covered the delay. In its Aug. 11 notice, RA said it was "exploring" removing tennis from Autumnwood and wanted to do the net removal, shade structures, new signage and bottle filling station all at once. Staff took comments at the courts on Aug. 22 and Aug. 26. The notice also said that if the change goes ahead, the winter play hours set in 2025 would stay in place.
Both projects are part of one swap, but they differ a lot in cost. Lake Newport is a $1.6 million rebuild with a fixed year in the capital plan. Autumnwood's half costs about one-twentieth as much and has been handled as a programming change voted on separately by the board. That vote determines how many courts pickleball gets once Lake Newport is tennis-only.
The rest of RA's courts
Outside Autumnwood, RA's other permanent pickleball site is a pair of courts on Colts Neck Road. Tennis has far more room. RA has 50 courts that allow tennis, including eight clay courts and 24 lighted courts for evening play. RA is also testing online reservations at the North Hills and Newbridge tennis facilities, where players can book courts two to seven days ahead. First-come paddle stacking is still how Autumnwood works.
Pickleball players have already raised the space issue with the board. In comments at a June 2026 board meeting, players asked for more dedicated courts, especially in South Reston, and described crowded courts, long waits and trips outside Reston to play. The July staff memo that proposed the swap also discussed criteria for future pickleball sites. It noted that new courts in Reston would likely be close to a Resource Protection Area and would need environmental review. FFXnow reported that the board was expected to consider those siting criteria together with the Autumnwood conversion.
For players in 2027, the result is fairly simple. Tennis gets a renovated six-court flagship at Lake Newport. Pickleball's main site is Autumnwood on Walnut Branch Road, with four courts now and eight if the conversion goes through. Colts Neck Road remains the only other permanent pickleball site. Board decisions and RA's capital calendar will determine any courts beyond those.
An RA capital project near your home, whether a court renovation, a splash pad or a trail upgrade, affects more than the weekend schedule. It also changes what buyers see and ask about when they look at nearby homes. If you live near Lake Newport, Autumnwood or another RA facility on the 2027 plan and want to know how that fits into a sale, Jeff Major Homes can walk you through it with a free home valuation.